Permitted Tariff Category | Tariff Structure |
Industrial
| All Regions except Dhofar | Dhofar Region |
September to April 12 Baiza per kWh | August to March 12 Baiza per kWh |
May to August 24 Baiza per kWH | April to July 24 Baiza per kWH |
Commercial | Flat Rate @ 20 Baiza per kWH |
Ministry of Defence | Flat Rate @ 20 Baiza per kWH |
Residential | 0 - 3000kWH | 3001-5000kWH | 5001-7000kWH | 7001-1000kWH | Above 10000kWH |
10Bz/kWH | 15Bz/kWH | 20Bz/kWH | 25Bz/kWH | 30Bz/kWH |
Government | 0 - 3000kWH | 3001-5000kWH | 5001-7000kWH | 7001-1000kWH | Above 10000kWH |
10Bz/kWH | 15Bz/kWH | 20Bz/kWH | 25Bz/kWH | 30Bz/kWH |
Agriculture and Fisheries | 0-7000 kWH | 7001 kWH & above
|
10 Baiza per kWH | 20 Baiza per kWH
|
Tourism
| 0-3000 kWH | 3001-5000kWH | 5000 kWH & above
|
10Bz.kWH | 15Bz/kWH | 20BZ/kWH
|